Project Communications

2014 Solarize Plano Project
Project Communications

Information Meetings

Enrollee Decision Process
  • Participant Decision Points - Solarize Plano Project enrollees will have three main decision points and decisions to make during the project timeline. Please review this document to obtain an understanding of these decisions and the corresponding timeline.
FAQs


2013 Solarize Plano Project (Historical information)
Project Communications
Information Meetings
Enrollee Decision Process
  • Participant Decision Points - Solarize Plano Project enrollees will have three main decision points and decisions to make during the project timeline. Please review this document to obtain an understanding of these decisions and the corresponding timeline.
FAQs
Net Metering
Enrollment Re-opened - Limited Time (Now closed)
  • Re-opened September 27, 2013 through October 31, 2013 (*** now closed ***)
  • For details, go to http://www.solarizeplano.org/ and follow the six steps described there.
Contracting COMPLETED - Surpassed goal of 80 kW+ (status of 10/29/13)
  • Number of site assessments completed - 52 total
  • Number and size of proposals submitted to enrollees - 49 total, 235.7 kW total
  • Number and size of contracts committed by enrollees - 25 total, 120.8 kW total
Project Introduction Information
  • **** Enrollment closed as of end of the day August 5, 2013 ***** The interest and participation has greatly exceeded expectations. The final total number of persons completing the signup form was over  200.
  • To learn more about the project and to enroll, go to http://www.solarizeplano.org/